Page 318 - Using MIS
P. 318

286       Chapter 7  Processes, Organizations, and Information Systems







                                          Receive Permit Application          Reject Permit



                                                          No
                                                Complete?


                                                    Yes





                                            Engineering Review




                                                          No
                                                Approved?


                                                    Yes
                                                                                        No
                                                  Need
                                                  Septic or  Yes
                                               Water Review?                       Approved?
                                                              Health Department Review
                                                    No
                                                                                        Yes



                                                  Need
                                                 Highway  Yes                      Approved?
                                               Dept. Review?                                  No
                                                             Highway Department Review
                                                    No                                  Yes
        Figure 7-21
        Building Permit Process,
        Old Version                                                                            Approve Permit



        sequential nature. Only after a permit had been approved or   office made three copies of the permit and distributed one to
        rejected by the engineering review process would they find out   each department. The departments reviewed the permits in
        that a health or highway review was also needed. Because each   parallel; a clerk would analyze the results and, if there were no
        of these reviews could take 3 or 4 weeks, applicants request-  rejections, approve the permit.
        ing permits wanted the review processes to be concurrent   Unfortunately, this process had a number of problems, too.
        rather than serial. Also, both the permit applicants and county   For one, some of the permit applications were lengthy; some in-
        personnel were frustrated because they never knew where a   cluded as many as 40 to 50 pages of large architectural drawings.
        particular application was in the permit process. A contractor   The labor and copy expense to the county was considerable.
        would call to ask how much longer, and it might take an hour   Second, in some cases departments reviewed documents un-
        or longer just to find which desk the permits were on.  necessarily. If, for example, the highway department rejected an
            Accordingly, the county changed the permit process to   application, then neither the engineering nor health departments
        that shown in Figure 7-22. In this second process, the permit   needed to continue their reviews. At first, the county responded
   313   314   315   316   317   318   319   320   321   322   323