Page 601 - Introduction to Business
P. 601

CHAPTER 16   Managing Business Operations  575


                 EXHIBIT 16.11
                 Bill of Material for an Office Chair



                                         Level 0   Office chair



                            Back             Seat             Chair
                 Level 1                                                   Fasteners (8)
                           cushion          cushion          frame


                           Adjuster
                 Level 2                   Base unit        Wheels (6)     Fasteners (3)
                          mechanism

                 Source: From Operations Management: Concepts in Manufacturing and Services, 2nd edition by Markland,
                 Vickery, and Davis. Copyright © 1998. Reprinted with permission of South-Western, a division of Thomson
                 Learning: www.thomsonrights.com. Fax 800 730-2215.


                 exactly 4 weeks each. Once the production rate strategy is broken down into weeks,
                 it is called the master production schedule. The master production schedule for  master production schedule A schedule
                 office chairs is provided in Exhibit 16.12.                              where the production rate strategy is
                                                                                          broken down into weeks
                    In addition, suppose that there are currently on hand 22 back cushions, 52 seat
                 cushions, 50 chair frames, 970 fasteners, 4 adjuster mechanisms, 77 base units, and  EXHIBIT 16.12
                 900 wheels. Lastly, assume that it takes one week to assemble the office chair and
                 the chair frame, and it takes two weeks to produce the other components.  Master Production Schedule
                                                                                          for Office Chairs
                    Using MRP logic, the operations manager would estimate the requirements for
                 chair frames as in Exhibit 16.13.  The number of chair frames requested comes
                                                                                                          Production
                 directly from the master production schedule for office chairs; that is, if 25 office  Week  (chairs)
                 chairs will be produced during week 1, then 25 chair frames will be requested at the
                 beginning of week 1. In turn, given that there are currently 50 chair frames on hand,  1    25
                 no chair frames will be required until the beginning of week 3. And because it takes  2     25
                 one week to assemble chair frames, the 25 chair frames that are required at the  3          25
                                                                                              4              25
                                                                                              5              50
                 EXHIBIT 16.13                                                                6              50

                 Requirements for Chair Frames and Wheels                                     7              50
                                                                                              8              50
                                                        Week
                   Chair
                   Frames       0      1     2      3      4      5     6      7     8
                   Requested           25    25     25     25    50     50     50   50
                   On hand      50     50    25      0      0     0      0      0    0
                   Required             0     0     25     25    50     50     50   50
                   Ordered              0    25     25     50    50     50     50    0


                                                        Week
                   Wheels       0      1     2      3      4      5     6      7     8
                   Requested            0   150    150    300   300    300    300    0
                   On hand     900    900   900    750    600   300      0      0    0
                   Required             0     0      0      0     0    300    300    0
                   Ordered              0     0      0    300   300      0      0    0


                 Copyright 2010 Cengage Learning, Inc. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part.
   596   597   598   599   600   601   602   603   604   605   606