Page 606 - Introduction to Business
P. 606

580     PART 6  Managing Business Operations, Management Information Systems, and the Digital Enterprise


             Control Decisions

             LEARNING OBJECTIVE 8
             Outline the control decisions about scheduling and quality.
                                     Once the operations manager has designed the production system and its products
                                     and has planned the production rate and the materials required along with their
                                     supply sources, as well as the inventory levels, he or she still has to make two major
                                     control decisions: scheduling and quality.


                                     Scheduling

        scheduling Allocating available  Scheduling decisions allocate available production resources to tasks, jobs, orders,
        production resources to tasks, jobs,  activities, or customers in a given time period. The capacity design decision con-
        orders, activities, or customers in a
        given time period            strains the production rate decision, which in turn restricts the scheduling deci-
                                     sion. A production schedule indicates what is to be done, when, by whom, and with
                                     what resources. Scheduling decisions vary with the type of process: project, job,
                                     batch, line, and continuous. In this introductory treatment, we consider the sched-
                                     uling decision only for job processes.
                                        One of the most widely used scheduling tools is known as the Gantt chart, first
                                     proposed by Henry Gantt in 1917. Exhibit 16.15 illustrates a scheduling decision for
                                     a job process using a Gantt chart.
                                        In this example, there are fours jobs A, B, C, and D that have to be scheduled in
                                     three work centers I, II, and III. The route stipulates the sequence in which jobs
                                     need to visit the work centers, as well as the machine hours required at each work
                                     center. For instance, first job D needs to go to work center I and be processed for
                                     three hours; next job D needs to go to work center III and be processed for two
                                     hours; and finally job D needs to go to work center II and be processed for one hour.
                                     The decision that the operations manager faces is how to schedule the jobs in the
                                     work centers so that all jobs are finished as soon as possible. The Gantt chart for the
                                     case where jobs are scheduled in the order A, B, C, D is
                                      • Job A is scheduled at work center I for hours 1 and 2, then at work center II for
                                        hours 3 to 5, and then at work center III for hours 6 to 9.
                                      • Job B is scheduled at work center III for hours 1 and 2, then at work center II
                                        for hours 6 and 7 (because hours 1 and 2 are not feasible, and hours 3 to 5 are
                                        already assigned to job A), and then at work center I for hours 8 and 9.
                                      • Job C is scheduled at work center II for hours 8 to 10 (because job C requires
                                        three hours, hence hours 1 and 2 are not sufficient and hours 3 to 7 are already
                                        assigned to jobs A and B), then at work center III for hour 11, and then at work
                                        center I for hours 12 to 14.
                                      • Job D is scheduled at work center I for hours 3 to 5 (because hours 1 to 2 are
                                        already assigned to job A), then at work center III for hours 12 and 13 (because
                                        hours 1 to 5 are not feasible, hours 6 to 9 are already assigned to job A, hour 10
                                        is not sufficient, and hour 11 is already assigned to job C), and then at work
                                        center II for hour 14.
                                     According to this first schedule, all four jobs can be finished in 14 hours.
                                        Now consider the second Gantt chart where jobs were scheduled in the order D,
                                     C, B, A. This second schedule is superior because all jobs are finished in 13 hours.
                                     The operations manager would keep trying different job schedules in order to find
                                     the one schedule where all jobs are finished as soon as possible.
                                        Variations of the Gantt chart can also be used for scheduling decisions in proj-
                                     ect and batch processes.


                 Copyright 2010 Cengage Learning, Inc. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part.
   601   602   603   604   605   606   607   608   609   610   611