Page 4 - F6 - Capital Allowances - Leases
P. 4
Example
In terms of a leasehold agreement of land, Builder, the
lessee, has to erect a factory (for sole use in their
manufacturing operations) to a value of R3 000 000
within a period of 18 months from the date of
commencement of the lease, which was 1 January 2014.
The lease is for a period of 20 years. On the expiry of the
lease, the factory will revert to the landlord without
compensation to Builder. At the end of the first year of
assessment (30 June 2014) the factory had not been
completed, but R1 250 000 had actually been spent on
its erection. The building was completed on 31 March
2015, at a total cost of R3 500 000, and the factory was
immediately let to tenants (that carries on a
manufacturing trade).