Project management tools and techniques
Tools and techniques used in planning
time – network analysis
3.1 Network analysis
Network analysis is used to analyse the inter-relationships between the tasks
identified by the work breakdown structure and to define the dependencies of each
task.
A Critical Path Analysis (CPA) or network diagram can be drawn to show these inter-
relationships and dependencies.
3.2 The network diagram
The diagram is made up of two parts: activity lines and nodes.
NAME OF ACTIVITY
Activity lines:
DURATION
The activity name and the duration of the activity are written on the arrow.
Nodes:
Nodes are numbered so that each node has a unique identifier.