Chapter 15




               Draw the network diagram:

                    Draw the basic shape and add the durations for each activity:





                                 A                          B


                                  8                        10
                                                                                    E

                                                                                    8
                                 C                          D


                                  6                         4




               Note: The network can be drawn in different ways. The following diagram would also
               correctly represent this project:



                                                           B                         E

                                 A                         10                        8

                                  8






                                 C

                                  6                        D
                                                            4




                                                                       DUMMY ACTIVITY LINE
                 This version uses a dummy activity line.
                                                                         DURATION = ZERO