3.6 Limitations and benefits of CPA
Limitations Benefits
Time consuming for large Helps identify all required
projects activities
Overly complex for small, short- Identifies dependent activities
term projects and those which can run in
parallel
Difficult to use for less routine
projects Identifies the activities on the
critical path
Identifies activities with float
Highlights the minimum
completion time for the project