               CHAPTER 10 – CONSTRUCTION CONTRACTS




                  Example 10.1


                  Step 1 Overall profit/loss on contract

                                                                 A             B             C
                                                               $000          $000          $000

                  Contract price                                 450           378           900

                  Costs to date                                 (346)         (421)         (198)
                  Costs to complete                               (43)        (151)     (unknown)
                                                                ––––        –––––       –––––––

                  Total estimated profit                          61          (194)     unknown

                  Step 2 % completion on work certified basis

                  A       338/450 =                75%

                  B       252/378 =                67%

                  C       180/900 =                20%


                  Statement of profit or loss (extract)

                                                                 A             B             C
                                                                $000         $000          $000
                  Revenue (% × contract price)                    338           252          198

                  Cost of Sales (% × total cost)                 (292)        (446)β        (198)
                                                              ––––––        ––––––         –––––

                  Gross profit/loss                                46         (194)             –