Overhead analysis





                           Absorption





               3.1   Overhead absorption

               The last stage in absorption costing is the absorption of the overheads into the cost
               units produced in the production cost centres. This is sometimes referred to as
               overhead recovery.


                                   Production               Production
                                  cost centre 1            cost centre 2



                                                Cost units

               The absorption can be done on a number of bases, the most common are:


                    physical units produced

                    labour hours worked

                    machine hours operated.

               Different production cost centres may use different bases.


               3.2   Overhead absorption rate

               An overhead absorption rate is used to calculate the amount of overhead to be
               picked up by each unit.


                                                               Budgeted production cost centre
                                                                             overhead
                Overhead absorption rate (OAR) =              ––––––––––––––––––––––––––––––
                                                            Budgeted quantity of absorption base

                                                              (units/labour hours/machine hours)