PROJECT AND RELATIONSHIP MANAGEMENT (E2) ‐ PRACTICE TASKS

                  Attachment:


                  From: CEO

                  Memorandum to all Board Members:

                  The project to redesign Crowncare’s website is due to commence shortly but already potential
                  problems have been identified with the proposed functionality of the new site and the fact that it
                  is not easy to navigate.

                  The Project Manager when questioned has expressed concern about the lack of initial discussion
                  surrounding project constraints. He feels that the extra time now needed (and therefore the rising
                  costs of the project) to improve the functionality are a result of these constraints not being fully
                  understood in the first instance. He estimates that the change to the functionality will delay the
                  project by several weeks.

                  The Board has had feedback from the project team members who have complained that there has
                  been a lack of visibility of the project manager. Team members have said that they were unaware
                  of any deadlines as they had not been shown any plan or schedule of work and this had made it
                  difficult to prioritise tasks and understand how they can contribute to the project.

                  I have called an emergency meeting with the Project Manager in order to come up with some
                  immediate solutions which could address the estimated project slippage.

                  Alison