A revision of F2 topics
1.4 Fixed, flexible and flexed budgets
1 Fixed budgets
A fixed budget is prepared before the beginning of
a budget period for a single level of activity.
Fixed, flexible and
flexed budgets
Four
2 Flexible budgets 3 Flexed budget
A flexible budget is also prepared A flexed budget is prepared at
before the beginning of a budget the end of the budget period.
period.
It provides a more meaningful
It is also prepared for a number of estimate of costs and revenues
levels of activity. and is based on the actual level
It requires the analysis of costs of output.
between fixed and variable As a result, the diversity and
elements. complexity of products has
increased.
Not all production overheads
are driven by level of activity.