Page 39 - Gi_Feb2020
P. 39

igem news – yppc


                 FIGURE 5  ORIGINAL HDPE IP GAS ROUTE             FIGURE 6  DRAINAGE CHAMBERS FOUND DURING 40MWE DERWENT SITE PREPARATION





















                 FIGURE 7 150MM CLEARANCE BETWEEN LV CABLE AND IP STEEL   FIGURE 8 SCHEMATIC OF DERWENT PHASE 1 GAS PRESSURE FLOW
                 GAS PIPE AT DERWENT























                 averages about 10°C. Given the required   operating pressure (MOP) of 7bar within   site, the demolition of part of the
                 pressure reduction from 38bar to 7bar,   a temperature range of 0°C to 40°C.   aforementioned power station revealed
                 and subsequently to 250/260mbar, a   PE100 and multilayer PE100/PE100   existing drainage chambers.
                 decrease in the temperature of the gas   pipes shall not be operated below 0°C.   Trial holes were carried out on
                 was expected at the outlet of the PRS                             the rest of the gas route to eliminate
                 from 10°C to about -10°C. This is due to   Solution A pre-heater module as shown   potential risks around utilities not
                 the Joule-Thomson effect.        in Figure 4 was incorporated to heat up   captured on the utility search.
                   For every bar of pressure reduction,   the gas to approximately 23.1°C.   Results showed that oil filled cables
                 there is a subsequent temperature   This was prior to the pressure   were located between 1.2m and 1.5m
                 reduction of 0.5°C. This poses a huge risk   let down, with an expected outlet   below the ground surface which
                 to the downstream gas infrastructure.   temperature of 8.1°C of gas on the   discounts a possibility of an open cut
                                                  downstream pipework. The boiler   installation or directional drill to install
                 Joule-Thomson effect In 1852, British   consumes an average of 82.60kWth of   either the gas pipe or the LV cable.
                 physicists James Prescott Joule and   gas at a flow rate of 9,937Nm³/h. This
                 William Thomson discovered that   is subject to weather conditions.    Power supply The ultrasonic meter and
                 temperature change can occur in gas as                            electronic devices on the PRS and pre-
                 a result of sudden pressure change over    Underground utility services and   heater module required a 380V 50Hz
                 a valve. This is referred to as the Joule-  structures UKPR’s proposed 40MWe site   AC 3ph 16Amp power supply.
                 Thomson effect.                  was situated at the old decommissioned   Due to limited information on the
                   As shown in Figure 3, the      Derwent power station.           underground utilities, I was faced with
                 temperature change pertaining to the   Unfortunately, the as-built drawing   the challenge of installing 305m of
                 Joule-Thomson effect can occur when a   for this site was incomplete and many   95mm AL cable below ground to the
                 flowing gas passes through a pressure   details were unknown. This posed   feeder pillar.
                 regulator, which acts as a throttling   a huge risk to the installation of the
                 device, valve, or porous plug.   HDPE IP gas pipe and the low voltage   Solution Based on the outcomes of
                                                  (LV) cable which would share the same   the trial holes, I concluded that the
                 Risk of temperature to downstream   trench as the gas pipe.       low voltage (LV) cable needed to be
                 infrastructure According to Gas Industry   The LV cable was required to supply   installed above ground on the steel gas
                 Standard (GIS) PL2:8 and IGEM/TD/3   power to the pre-heater module and the   pipe, allowing approximately 150mm
                 Edition 5, all PE100 SDR11 need to   ultrasonic meter.            clearance in reference to IGEM/UP/2
                 be able to operate at a maximum    In preparing our proposed 40MWe   Edition 3/Clearances. See Figure 7.



                                                                                                                        39



                                                                                                                  16/01/2020   16:02
        IGEMNews_YPPC.indd   2
        IGEMNews_YPPC.indd   2                                                                                    16/01/2020   16:02
   34   35   36   37   38   39   40   41   42   43   44