Page 40 - Gi_Feb2020
P. 40

igem news – yppc


                 FIGURE 9 REPOSITIONED GAS RECEPTION KIOSKS AND ABOVE GROUND STEEL GAS PIPE ROUTE  FIGURE 11 NEW FILTERS REPLACED ON BOTH STREAMS


























                                                                  FIGURE 12 COMPLETE 110 MWHT GAS CONNECTION CURRENTLY DELIVERING 40MW OF ELECTRICITY
                                                                  TO THE GRID
                 FIGURE 10 INSTALLED RECALIBRATED EXISTING FILTER ON A STREAM AT DERWENT

















                   Gas route The installation of 90m of   required to meet the CM15 deadline. To   overall timescale. The new filters were
                 HDPE IP was proposed on the access   achieve this, the project was split into   later installed with no impact to gas
                 road. The drainage chambers cut   phases 1 and 2.                 flow as shown in Figure 11.
                 across the access road and introduced     a) Phase 1: 110 MWht gas load capacity   5. Extra man hours: I further reduced
                 a potential risk to any possible   to generate 40MW of electricity.   the lead time by engaging the onsite
                 excavation, which would affect the     b) Phase 2: Full gas load capacity of   workers on extra working hours and
                 integrity of the road.           600MWth to generate 200MW of     weekend working with appropriate
                                                  electricity.                     supervision.
                 Solutions As shown in Figure 9, I had   2.  Hiring of PRS and pre-heater module:
                 to reposition the gas reception kiosk   I had to hire a containerised pre-  Conclusions
                 eliminating the installation of the   heater model and PRS from the   Ultimately, the project was successfully
                 90m of HDPE IP gas pipe which had   Netherlands. Figure 8 shows a   delivered in only eight months – a third
                 been proposed.                     schematic of the gas pressure flow.   of the scheduled time. This was a great
                   As a result of the trial holes, 60 per   3. Acceleration of manufacturing time:   achievement and one of which I am
                 cent of the HDPE was replaced with   I went ahead of the supply chain to   proud. Figure 12 shows the complete
                 above ground steel gas pipe. The cost for   accelerate manufacturing time for the   and operational 40MWe Derwent site.
                 above ground steel gas pipe was offset by   long lead items i.e., ultrasonic meter,
                 the recovered cost of the 90m of HDPE.   valves, etc.             Future optimisation
                                                    This had a further reduction on   Although it requires additional heating,
                    Lead time                     timescales.                      replacing the J-T valve used in the
                 At inception, I was tasked to accelerate   4. Recalibration of an existing filter:   project with a turbo expander has a
                 the 24 months lead time to deliver 600   Given that the filter manufacturing   potential to recover electric energy
                 MWht of gas (200MW of electricity)   lead time could not be accelerated,   generated during the pressure reduction.
                 secured from Cadent.             I suggested that an existing filter be   The waste heat from the reciprocating
                   These are strategic decisions I   recalibrated and installed, as shown in   engines can be recovered to
                 deployed to achieve it:          Figure 10.                       compensate for the additional heating
                                                    This was an interim solution prior   requirement for turbo expanders.
                 Solutions                        to the availability of the appropriate   Optimising the site will create
                 1. Delivery of the project in phases:   filters. This was successfully carried   significant fuel cost savings for the
                 40MW of electricity (110MWth gas) was   out and had a significant impact on the   lifecycle of the project.



          40



                                                                                                                  16/01/2020   16:02
        IGEMNews_YPPC.indd   3                                                                                    16/01/2020   16:02
        IGEMNews_YPPC.indd   3
   35   36   37   38   39   40   41   42   43   44   45