Node 3: L3 = min { Lj – t3j} = min {39 – 16, 67 – 24} = 23
Node 2: L2 = L5 – t25 = 57 – 19 = 38
Node 1: L1 = min {Lj – tij}= min { 38 – 20, 23 – 23, 39 – 8} = 0
To evaluate the critical nodes, all these calculations are displayed in the flowing table:
Task Normal Earliest time Normal time Float
Time
i,j (days) Start(Ei) Finish(Ej) Start(Li) Finish(Lj) Total Free Indepent-
ent
(1, 2) 20 0 20 18 38 18 0 0
(1, 3) 23 0 23 0 23 0 0 0
(1, 4) 8 0 8 31 39 31 31 31
(2, 5) 19 20 39 38 57 18 0 -18
(3,4) 16 23 39 23 39 0 0 0
(3,7) 24 23 47 43 67 20 20 20
(4,5) 0 39 39 57 57 18 0 0
(4,6) 18 39 57 39 57 0 0 0
(5,6) 0 39 39 57 57 18 18 0
(5,7) 4 39 43 63 67 24 24 6
(6,7) 10 57 67 57 67 0 0 0
To above table shows that the critical nodes are for the tasks (1,3), (3,4), (4, 6), (6,7).