Page 18 - OPERATIONS RESEARCH
P. 18

From the above network diagram, we observe:

                   CPM: 1->3->5->6->7    OR B->E->G->H.
                   Expected duration of the project is 19 days.

                   The variance of the project length is: σ  =1+4+4+0.1  =1+4+4+0.108 = 9.108.
                                                        2
                                                                               Or σ = √9.108= 3.02.
                                                           e
                   P(z≤ 1.645)=0.5 + 0.45 = 0.95.
               And then, (Ts – Te)/σ =1.645.
                                    e
               Or Ts=19+3.02×1.645=24 days.
               Hence,  24  days  of  project  completion  time  will  have  95%  confidence  of  completion  in  the

               scheduled time.

                   iii.   When  the  average  duration  of  activity  F  increases  to  14,  the  path  C->F->H  also
                          becomes critical. The standard deviation of new critical path is :

                   σ = √9. 108+2=3.36.
                    e
                   P(z<1.645)= 0.95 gives us (Ts – 19)/3.36=1.645.
                   Ts = 19 + 3.36 ×1.645 = 24.52 days.

               Hence the project completion duration of 24.52 days will have 95% confidence.


               DISTINCTION BETWEEN PERT ND CPM:

                            Both  PERT  and  CPM  are  managerial  techniques  for  planning  and  control  of  large

               complex projects. Both are techniques to network analysis a network is prepared to analyze inter-