Page 15 - OPERATIONS RESEARCH
P. 15
It is apparent from that the critical path comprises the tasks (1,3), (3,4), (4,6), (6,7). This path
represents the shortest time to complete the entire project.
PROBABILITY CONSIDERATION IN PERT
Under the conditions of uncertainty, the estimated time for each activity for PERT network is
represented by a probability distribution. This probability distribution of activity time is based
upon three different time estimates made for each activity. These are as follows
=the optimistic time, is the shortest possible time to complete the activity if all goes well,
= the pessimistic time, is the longest time that an activity could take if everything goes wrong,
= the most likely time, is the estimate of the normal time an activity would take. If only one
time were available, this would be it. Otherwise it is the mode of the probability distribution.
The range specified by the optimistic
time ( ) and pessimistic time ( ) estimates
supposedly must enclose every possible
estimate of the duration of the activity. The
most likely time ( ) estimate may not
coincide with the midpoint ( + )/2 and
may occur to its left or to its right as given,