   UPDATE ON SAIF PHASE1 FUNDING APPLICATION



  The NRF and iThemba LABS management would like to thank the project team, supported by many role-players at
  iThemba LABS and collaborators, for the sterling work achieved thus far.




                                          1. A strongly positive letter of support from  Treasury allocated R167.9m for the
                                          the DST acknowledging  the value of the  project as indicated in the mid-term
                                          project for iThemba LABS, NRF, NSI and  budget policy statement for the 2018/2019
                                          the country.                             financial year. The funding will be used to
                                                                                   kick-start phase 1 of the SAIF project
                                          2.Formal support and approval of the    (ACE Isotopes), which is centered on the
                                            SAIF project from the Minister of Science   acquisition of a 70 MeV cyclotron that will
                                          and Technology Minister Kubayi-Ngubane.   be used for isotope production and
   Over the past few months, much progress                                         research; and the implementation of the
   was realized with the application to secure   3.Successful submission to the    low-energy radioactive ion beam (LERIB)
   funding  for  the  South  African  Isotope    Joint Technical Committee of the Budget   project.
   Facility (SAIF) Phase 1.                Facility on Infrastructure (BFI) of the
                                           National Treasury.                     The  DST's  evident  support  of  the  first

   iThemba LABS' project team, working with   The technical committee recommended  phase  of  SAIF  ushers  in  a  new  era  for
   the National Research Foundation (NRF)    the project to the Steering committee  iThemba  LABS  as  the  beams  from  the
   Corporate  office,  has  been  burning  the    within BFI in September 2018.   SSC will be dedicated for nuclear physics
   midnight oil to respond to urgent questions                                    and  radiation  biophysics  research.  This
   and clarifications from the Department of   4.Minister Mmamoloko Kubayi-Ngubane's  will not only more than double the beam
   Science  and  Technology  (DST)  and   announcement during her address at the  time  available  for  research,  thereby
   National  Treasury  (NT)  on  the  business    COMEX6 conference that the iThemba  providing  more  beam  time  for  student
   case submitted by iThemba LABS for SAIF    LABS SAIF project is supported by her  training projects, but it will also enhance
   Phase 1.   During the two months period,    Ministry, and that she has engaged with  the  training  of  accelerator  physicists,
   several positive steps and outcomes were    the Minister of Finance to provide funding  engineers and technicians.
   achieved. These include (amongst others):   for the project.