Page 203 - Civil Engineering Project Management, Fourth Edition
P. 203

183
                                                          Measurement and bills of quantities
                          contractor a false impression of the nature of the work. It needs to be borne in
                          mind that sometimes it is the practice to ‘agree bill quantity’ for an item for
                          payment if there is no obviously large variation from what the drawings show.
                          Hence quantities should represent a best estimate of what will occur, in order
                          to be fair to both contractor and employer.
                            The problem of rock.  A problem occurs when billing rock which may be
                          suspected but whose incidence is not known – as in the case of a long pipeline
                          where it is impracticable to sink enough borings in advance to discover the
                          depth and extent of rock everywhere. Sometimes a provisional quantity is put
                          in for rock, but if the extent of rock is not known, the problem is to decide what
                          provisional quantity is to be put in the bill? Also how can the tenderer price
                          such an item when the actual quantity to be encountered is only ‘provisional’.
                          Instead, it is suggested, a provisional sum should be included in the bill for rock
                          excavation, and a price for excavating rock should be agreed with the con-
                          tractor, if rock is encountered.
                            However, a consequent problem is that, if rock is encountered, it will almost
                          certainly delay the work, so the contractor will put in a delay claim. Despite
                          this, there is much to be said for negotiating a rate when rock is encountered,
                          because widely different methods – and therefore costs per unit excavated –
                          will apply according to the nature and direction of bedding of the rock encoun-
                          tered (see Section 15.7).
                            Provisional quantities for other matters should likewise only be used with
                          care. They should relate to something known to be required, the quantity
                          being a reasonable judgement as to what might be required. This could apply
                          to such matters as bedding pipes on soft material, or bedding and haunching
                          pipes in concrete, or fully surrounding pipes in concrete where the actual
                          extent of such work depends on the site conditions encountered.



                          15.6 Billing of quantities for building work


                          Quite complicated buildings often form part of a civil engineering project, for
                          example power station buildings, pumping stations, stores, administrative
                          offices or laboratories. The CESMM gives units of measurement for some
                          common building operations, but the nature of building work is so diverse that,
                          in practice, many more items than shown in CESMM will be found necessary.
                            The CESMM will usually be found suitable for billing all work required to
                          complete the framework, walling, cladding and roofing to buildings, and such
                          matters as pipework, roads, sewerage, landscaping and fencing. Other build-
                          ing items primarily cover the interior finishes, carpentry and joinery, and other
                          miscellaneous matters. These can be measured by some simple method a civil
                          contractor will understand, since he will have experience of building work as
                          well as civil engineering. It is not necessary to follow all the details of the stand-
                          ard method of measuring building work, for example the many ‘extra overs’
                          listed in that method for brickwork. The preamble to the bills of quantities
   198   199   200   201   202   203   204   205   206   207   208