Page 208 - Civil Engineering Project Management, Fourth Edition
P. 208

Civil Engineering Project Management
                          188
                          sub-contract. It is true that, under Clause 59(1) the contractor has to have a
                          ‘reasonable objection’ for refusing to employ a nominated sub-contractor, but
                          this constraint is of little value in practice. There can also be refusal of either
                          party to accept the other’s terms for payment – although Clause 59(7) of the
                          ICE Conditions endeavours to protect a nominated sub-contractor by provi-
                          ding for direct payment to him if the main contractor fails to pay him.
                            If the contractor or nominated sub-contractor will not enter a contract
                          between them for any reason, the nomination fails. The engineer then has to
                          nominate another sub-contractor, or ask the contractor to do the work himself
                          or find his own sub-contractor. This mixing of responsibilities between the
                          employer and main contractor for the performance of a nominated sub-
                          contractor leads to frequent disputes. If the nominated sub-contractor fails to
                          do the work or goes into liquidation, the employer must take action without
                          delay, since the main contractor has no duty to carry out the work himself
                          and will claim for any delay in getting it done. Further, if the sub-contractor’s
                          work proves unsuitable or not fit for its purpose, the main contractor will deny
                          responsibility (unless he was expressly charged in the terms of the sub-contract
                          to take such responsibility – which is unlikely) since he had no choice in the
                          selection of the sub-contractor or the product.
                            The extensive disputes which have arisen over the years on these matters,
                          more particularly in building work with its wider use of nominated sub-
                          contractors, has led many engineers to take the view that use of nominated
                          sub-contractors in civil engineering should be avoided wherever possible.
                            The problems most often arise from late completion or defective perform-
                          ance by a nominated sub-contractor which affects the contractor or his other
                          sub-contractors. A possible way to avoid this is to specify the work in detail,
                          providing for its payment by measure under appropriate bill items. Or, if spe-
                          cially skilled or experienced workers are required to do the work, there is no
                          reason why this cannot be specified by calling for particular craft skills and
                          requiring evidence of same. Alternatively, if only one firm can provide the spe-
                          cial techniques required, the letting of a separate contract for such work can be
                          considered. Although the organization of separate contracts has to be efficiently
                          managed (as described in Section 5.6), the advantage is that the engineer retains
                          direct control over the specialist’s work and can act to avoid or solve problems
                          arising from late delivery or defective work. Where a nominated sub-contractor
                          is to supply only certain items, the employer may be persuaded to order the
                          materials direct and store them in advance of being needed; or the contractor
                          may be instructed to order them early and can be paid for offloading and
                          storing them on site under items provided in the bill of quantities.



                          15.9 Prime cost items


                          When a nominated sub-contract is intended but not yet chosen, a prime cost
                          item can be inserted in the bill of quantities by the engineer to cover the work
   203   204   205   206   207   208   209   210   211   212   213