Page 213 - Civil Engineering Project Management, Fourth Edition
P. 213

Measurement and bills of quantities
                                                                                              193
                          The ‘specified requirements’ (2) cover accommodation and services for the
                          engineer’s site staff, tests on materials, etc., and a range of temporary works
                          that the engineer might wish to itemize.
                            The difference between temporary works the engineer itemizes as ‘specified
                          requirements’ under Division 2 of the Class A bill, and the temporary works
                          which a tenderer adds as ‘method-related’ items under Division 3 should be
                          noted. The former have to be fully specified by the engineer in the contract;
                          the latter do not, being left to the tenderer to describe. Thus if the contractor
                          is required in the specification general clauses to construct some temporary
                          access road, then if the engineer itemizes it as a ‘specified requirement’ in Div-
                          ision 2 the details of it must be fully described in the specification or con-
                          tract drawings. If the engineer does not know how the access road should be
                          constructed because he does not know what traffic the contractor will put on it,
                          then he should not itemize it in Division 2 but leave it to the contractor to add
                          in Division 3 as a method-related item, if he so wishes.
                            It is important to follow the standard method requirements exactly, or prob-
                          lems of interpretation leading to claims from the contractor may arise. Of course
                          the contract can expressly state that items in the Class A Preliminaries Bill are
                          not drawn up in accordance with the standard method; but then care has to be
                          taken to define what each item entered covers so there is no ambiguity.



                          Problems with Civil Engineering Standard Method of
                          Measurement


                          The whole concept of payment for temporary works as set out in CESMM can
                          be called into question, as it creates potential ambiguities. The engineer may
                          choose not to itemize any temporary works under ‘specified requirements’
                          because he leaves such works for the contractor to decide. But the contractor
                          may maintain that the list of temporary works given in CESMM A.2.7 (such as
                          traffic diversion, access roads and de-watering) entitles him to payment for
                          those works on the same principle as – when an item which CESMM lists for
                          measurement is found missing – the item has to be added to a bill (see end of
                          Section 17.2). To avoid this ambiguity the preamble to the bill should state that
                          Class Aitems shall be measured only to the extent they are included in the con-
                          tract at the time of the award; thus fixing the temporary work items measured.
                            Another difficulty arises with method-related items. CESMM clauses state
                          that a method-related charge does not bind the contractor to use the method
                          defined (Clause 7.5); is not subject to admeasurement (Clause 7.6); and is not to
                          be increased or decreased for any change of method adopted by the contractor
                          (Clause 7.8). But when the engineer orders a variation of some permanent
                          work, the contractor may claim that bill rates for similar work do not apply,
                          because the temporary works associated with that work have changed but
                          the method-related item of charge remains fixed. This can raise debatable
                          issues concerning method-related charges which are defined as not subject to
   208   209   210   211   212   213   214   215   216   217   218