Page 209 - Civil Engineering Project Management, Fourth Edition
P. 209

189
                                                          Measurement and bills of quantities
                          and/or materials to be supplied by the nominated sub-contractor. The sum
                          entered by the engineer is that which he estimates will cover the sub-contractor’s
                          charges; the actual charge made by the sub-contractor being refunded to the
                          main contractor. Two additional items are added which tenderers can price.
                          One consists of a lump sum to cover the general facilities the contractor is to
                          provide for the sub-contractor; the other, expressed as a percentage of the
                          prime cost, is to cover all the contractor’s other charges and his profit.
                            The general facilities as defined in CESMM are deemed to cover – access;
                          use of scaffolding, hoists, contractor’s messrooms and sanitation; space for
                          any office and storage the sub-contractor sets up; together with light and
                          water. If more facilities than this are required, the CESMM requires this to
                          be expressly stated. Such extra facilities are often required, such as provision
                          of power, labouring assistance, use of crane, etc., and these have to be defined.
                          If, however, the sub-contractor supplies materials only, the lump sum is
                          deemed to include the contractor’s unloading, storing and hoisting of materials
                          delivered.
                            One practice to be avoided is to permit a sub-contractor chosen by the con-
                          tractor to submit his quotation only to the contractor. This could lead to the
                          sub-contractor including in his quotation for doing some work that is paid for
                          elsewhere in the contractor’s contract, resulting in double payment to the con-
                          tractor. A preferable approach is for the engineer to call for quotations from
                          sub-contractors to be submitted to him.


                          15.10 The preliminaries bill and method-related items


                          A preliminaries bill lists items which apply to the contract as a whole, such
                          as insurance of works, offices for the resident engineer, provision of laboratory,
                          surveying equipment, transport, telephone and tests on materials or the
                          works. The units of measurement will be appropriate to the type of item,
                          lump sum, or per week or month, or per number of tests, etc. Sometimes an
                          item needs to be split into two parts, such as a lump sum for provision of the
                          engineer’s site office, with a second item for its maintenance per week or
                          month. Such items listed by the engineer in the bill must be supported by
                          descriptions in the specification stating exactly what the contractor is to pro-
                          vide. See Fig. 15.1 which shows part of the first page of a preliminaries bill
                          drawn up according to CESMM.


                          Temporary works


                          The engineer may list temporary works the contractor has to provide, such
                          as access roads, a temporary sewage treatment plant and similar. The listing
                          of such temporary works permits the contractor to put a price to them, which
                          may be to his advantage. Insurance is costly, so that if a tenderer prices this
   204   205   206   207   208   209   210   211   212   213   214