Page 206 - Civil Engineering Project Management, Fourth Edition
P. 206

Civil Engineering Project Management
                          186
                            Thrust blocks for pipelines have to be constructed against vertically cut
                          undisturbed ground. It avoids argument if items for thrust blocks to dimen-
                          sions shown on the drawings are followed by an extra-over item for trimming
                          sides of excavation adjacent to thrust blocks to the vertical, including any back-
                          filling between a thrust block and the vertical excavated face with concrete.
                          Under the CESMM thrust blocks are measured per cubic metre inclusive of
                          concrete, formwork, reinforcement, etc. For large pipes requiring major blocks
                          it may be better to deviate from the standard method by treating these blocks
                          as structures in their own right.
                          Earthwork construction


                          Earthwork construction is measured as the net volume as placed. The source
                          of the filling should be stated. All information available about the nature of
                          the proposed fill material should be supplied to tenderers so they can make
                          their own estimate of the bulking factor of loose filling, its weight per unit
                          volume loose and when compacted, etc. When the filling is to be obtained
                          from a borrow pit, information concerning the extent and characteristics of
                          the borrow pit material and its location should be provided in the tender
                          documents.
                            If specified material for filling is to be obtained from selected material from a
                          borrow pit, the removal or set aside of unsuitable material from the borrow pit
                          has to be included in the rate for filling. It may also be necessary to include
                          re-handling of the unsuitable material in order to put it back into the borrow pit.
                          It is impracticable to measure the unsuitable material because some may be
                          worked around and left in situ. Hence it is important to define what the rates for
                          placing filling obtained from a borrow pit are to cover. Failure to include any
                          necessary double-handling of unsuitable material can result in a large claim for
                          extra payment from the contractor. It is advisable to give separate items for
                          stripping overburden from the borrow pit, and an item for reinstatement of
                          the borrow pit. The specification should set out all the requirements needed
                          for reinstatement which it should then be possible to bill as a lump sum item for
                          pricing. One point to note is that when ‘suitable material’ has to be taken from
                          a borrow pit, it may be helpful to specify instances of ‘unsuitable material’ also.


                          Concrete


                          Concrete in situ is measured in the CESMM as two operations: (i) supply
                          according to various quality grades; and (ii) the placing of concrete according
                          to its location in beams, columns, slabs, etc. This suits the modern practice
                          in the UK and similar developed countries where widespread use is made
                          of ready-mix concrete delivered to site. The totals of concrete in the various
                          grades must therefore sum the same as the relevant placing items per grade.
   201   202   203   204   205   206   207   208   209   210   211