Page 210 - Civil Engineering Project Management, Fourth Edition
P. 210

Civil Engineering Project Management
                          190














































                          Fig. 15.1. Typical example of the first page of a preliminaries bill, drawn up according to
                          CESMM Class A requirements, and priced by tenderer

                          item, he can be reimbursed his expenditure on it as soon as he shows evidence
                          of obtaining it. He does not have to wait for its reimbursement as he would
                          have to if he spread the cost over the constructional items. Also, a priced item
                          for such as the site sewage treatment works to be provided by the contractor is
                          of advantage to the employer, since payment for such works can be withheld if
                          the plant is not as specified or does not work properly. However, the pricing of
   205   206   207   208   209   210   211   212   213   214   215