Civil Engineering Project Management
190
Fig. 15.1. Typical example of the first page of a preliminaries bill, drawn up according to
CESMM Class A requirements, and priced by tenderer
item, he can be reimbursed his expenditure on it as soon as he shows evidence
of obtaining it. He does not have to wait for its reimbursement as he would
have to if he spread the cost over the constructional items. Also, a priced item
for such as the site sewage treatment works to be provided by the contractor is
of advantage to the employer, since payment for such works can be withheld if
the plant is not as specified or does not work properly. However, the pricing of