                          Fig. 15.2. Typical method-related items entered by a tenderer – one item wrong


                          Division of items in the preliminaries bill


                          The standard method has five main divisions or categories of items that can
                          be put in the Class A preliminaries bill:
                          1. ‘contractual requirements’ (bond and insurances);
                          2. ‘specified requirements’;
                          3. the ‘method-related charges’ referred to above which the tenderer is to insert;
                          4. ‘provisional sums’;
                          5 and 6. ‘Nominated sub-contracts’, which include work done on site, and
                             work, such as manufacture, done off site respectively.