Page 205 - Civil Engineering Project Management, Fourth Edition
P. 205

185
                                                          Measurement and bills of quantities
                          explosives or hydraulically operated rock hammers or compressed air-operated
                          rock breaking equipment before being removed’. From the contractor’s point of
                          view this is not entirely satisfactory since it would exclude payment for rock
                          he can get out with a suitably powerful digger able to cope with hard bands,
                          albeit with difficulty and at a slow rate, involving substantial extra cost. Hence
                          mechanical ripping forms a third category which may warrant separate meas-
                          urement where hard bands of material are encountered that cannot be broken
                          up by scrapers or the normal bucket excavator, but do not qualify as rock.
                          Measurement of rock excavated for valuation is not easy; it is best done by a
                          member of the resident engineer’s staff and the contractor’s staff viewing the
                          excavation together in order to agree on the rock volume.
                          Working space


                          Contractors often claim payment for additional excavation to provide working
                          space, despite the fact that most contracts and methods of measurement clearly
                          state that only the volume vertically above the limits of foundations will be
                          measured for payment. Therefore if some exterior tanking or rendering to a
                          basement is required, it is advisable to repeat in the item for this that the con-
                          tractor must allow in his rates for any working space he requires.


                          Pipelines


                          Trench excavation for pipelines is covered piecemeal in Classes I, K and L of
                          the standard method (Class J covers provision of fittings and valves). Trench
                          excavation to pipe invert level is included in the supply, laying and jointing of
                          pipes per linear metre in Class I. Excavation below that for bedding is included
                          in the supply and placing of bedding material, also per linear metre, in Class L.
                          Extra excavation for manholes is included in the rates for manhole construc-
                          tion in Class K. Rock is an extra item payable per cubic metre in Class L. All
                          pipework excavation items include backfilling.
                            Excavation of joint holes is not specifically mentioned so needs to be speci-
                          fied as included in the rates.
                            If the standard method of measurement is not used, it can prove simpler to
                          take excavation (including backfilling) separately from pipe supply and lay-
                          ing. The maximum and average depth of trench, including any depth required
                          for bedding, is stated for any given length of pipeline and is taken for payment
                          per linear metre. Excavation for joint holes should be stated as not measured
                          but included in the rate for trench excavation. The drawings should show the
                          standard trench widths taken for payment, and the depth of any bedding.
                          Rock is paid for as an extra over per cubic metre within the payment limits, the
                          rate to include for overbreak and backfilling thereof. Bedding, haunching and
                          surrounding are measured per linear metre for supply and placing.
   200   201   202   203   204   205   206   207   208   209   210