Page 218 - Civil Engineering Project Management, Fourth Edition
P. 218

Civil Engineering Project Management
                          198
                          are done according to some computer package which is unfamiliar to the
                          resident engineer, or if no sketches are provided by the contractor to explain
                          how his quantity has been calculated.
                            Some items will need measurement in the field, such as trench depths for
                          pipelines, excavation and mass concrete to foundations, etc. This may be done
                          by the resident engineer’s inspector who agrees the measurement with the
                          appropriate foreman, a written advice note being sent immediately to the
                          contractor giving the agreed figures. Sometimes joint measurement is arranged.
                          Other quantities can be taken from drawings if no variation has occurred.
                          Where an item of work is only partly done, a rough estimate of the proportion
                          done should be agreed with the contractor. Sometimes all but a minor aspect
                          of an item is completed, for example, final painting of valves in a valve cham-
                          ber. It is simpler to certify the item in full rather than making some trivial
                          reduction, making a note to remind the contractor if he fails to complete
                          the painting.
                            If work has been done so badly that it cannot be accepted, no payment
                          should be certified for it. If the contractor has agreed to do some remedial work
                          that will make it satisfactory, some partial payment can be made. All depends
                          on the circumstances. With a reputable contractor and a responsible agent
                          there is no reason to assume that verbal promises will not be carried out. With
                          good contractors most agreements are verbal anyway, and any paperwork is
                          only for the purposes of record.
                            Some agents leave the contractor’s quantity surveyors to prepare the con-
                          tractor’s accounts. When the quantity surveyors are approached and asked
                          not to repeat in every account items of claim previously struck out as being
                          invalid, they may reply they have no authority to remove an item once it has
                          been put into an account. Continued practice of this kind means that, as the
                          measurement gets larger, the resident engineer may have to make an increas-
                          ing number of corrections to items, page totals, and bill summaries. If the engin-
                          eer is unable to get the practice altered – if necessary by direct approach to the
                          contractor’s senior personnel – it at least eases the problem to insist, from the
                          beginning, that all extras, added items and claims are billed on a separate
                          sheet, or added at the end of each bill.



                          16.3 Payment for extra work, dayworks and claims


                          When extra work has been ordered then, if any of such extra work has been
                          done by the contractor, there should be some payment for it in the next
                          interim payment certificate even if the rates for such extra work have not been
                          agreed. The reason for this is that the ICE conditions provide that work done
                          shall be measured monthly and paid for within 28 days of the contractor sub-
                          mitting his account for same. Any dispute about the exact rate or amount for
                          some extra should not therefore delay payment of what the engineer con-
                          siders a reasonable amount. Otherwise the contractor could claim he was not
   213   214   215   216   217   218   219   220   221   222   223