Page 220 - Civil Engineering Project Management, Fourth Edition
P. 220

Civil Engineering Project Management
                          200
                          or if not, payment will be dependent on whether they are fixed or time-related.
                          Fixed sums would be paid as mentioned above for ordinary lump sums, but
                          problems can arise if the item description is imprecise. Thus if the contractor
                          has added some method-related item for ‘scaffolding’ or ‘site transport’ as a
                          fixed sum, it has to be further defined to relate to some specific scaffolding or
                          specific transport; otherwise it is too vague to identify and cannot be paid until
                          substantial completion.
                            When method-related sums are time-related they are paid in monthly
                          instalments, but the proportion paid will depend on when completion of the
                          relevant task will be reached. Thus if an item is completed when substantial
                          completion is achieved, and the programmed time for this is 18 months then,
                          1/18th payment is added at the end of each month. But if it then appears that
                          substantial completion will not be reached until month 20, the total payment
                          due at month 7 is 7/20ths. This is irrespective of whether the delay in comple-
                          tion is due to the contractor’s tardiness or to an authorized extension of the
                          contract period. The reason for this approach is that method-related items
                          are defined as covering ‘costs not to be considered as proportional to the
                          quantities of the other items’. If an extension of the contract period has been
                          granted, then any claim for extra payment on that account is a separate mat-
                          ter to be decided by the terms of the contract. The lump sum payable under a
                          method-related item remains unaltered.
                            An adjustment item in the form of a lump sum (see Section 15.11) is paid
                          in the same proportion as the total payment due under other items less reten-
                          tion, bears to the total contract sum, less the adjustment item. If a percentage
                          adjustment has been quoted, this is applied to the total amount payable under
                          bill items and variations. In both cases the retention money is deducted after
                          adding in the adjustment item.



                          16.5 Payment for materials on site


                          The ICE conditions and similar permit payment to be made to cover part
                          of the cost to the contractor of materials delivered to site but not yet built into
                          the works. This can ease the contractor’s cash flow situation and is of advantage
                          to the employer in encouraging early supply of materials so that unexpected
                          shortages or late deliveries are less likely to hold up progress. In contracts that
                          contain such a provision, tenderers can be expected to reduce their prices in
                          anticipation of the expected financial benefit.
                            Certifying payment for materials on site is left to the discretion of the engin-
                          eer. Under ICE conditions Clause 60(2)(b) he has to certify such amounts (if
                          any) as he may consider proper, not exceeding a percentage of the value as
                          stated in the contract. In this he may need to act carefully because, even though
                          material has been delivered to site, it might still remain the property of the
                          supplier until he has been paid for it by the contractor. If the supplier falls
   215   216   217   218   219   220   221   222   223   224   225