Interim monthly payments
205
the contract. If any are applicable, the employer may wish to deduct them
from any payment due to the contractor, otherwise they may be more difficult
to recover later. At completion the engineer will need to re-assess any exten-
sion of time due to the contractor and advise the employer regarding any
damages due. Deduction of damages is not a matter for the engineer to certify,
but for the employer to decide and apply.