Page 228 - Civil Engineering Project Management, Fourth Edition
P. 228

Civil Engineering Project Management
                          208
                            In some international contracts, any review of rates or prices is restricted
                          to changes in individual quantities exceeding a given percentage. If it were
                          intended that all changes in quantity justified a different rate, then the rates
                          would largely become irrelevant. In practice therefore rates are seldom altered
                          for what might be termed ‘natural’ variation of quantities. Most variations that
                          are large enough to require re-consideration of rates stem from an instruction
                          issued by the engineer or resident engineer and this is a different matter dealt
                          with in Section 17.4. Occasionally an item gets missed from a bill, which the
                          contract or method of measurement provides should have been measured.
                          Rates for these must also be set by the engineer in the same manner, but with-
                          out there being any instructed change.
                          17.3 Ordered variations


                          Many types of contract allow the engineer to order variations but, as mentioned
                          in Section 8.4 his powers to do so are usually restricted to changes that are
                          necessary or desirable for completion of the works, including any changes
                          requested by the employer. By this means the employer, through the engineer,
                          can obtain the result he wishes if his ideas and desires have altered since he
                          awarded the contract. But if the employer wishes to introduce an entirely new
                          piece of works or otherwise alter the basis of the contract, he can do this only by
                          agreement with the contractor. The intention is that the works as contracted
                          will still be built, that is, the same concept or result will be achieved but the
                          detail may alter. This is essential, since the contract gives the contractor the duty
                          and the right to carry out the contract works, and the contract will maintain
                          those rights even if the works are varied.
                            The resident engineer may sometimes receive a request from an employee of
                          the employer to make some addition. He should refer the request to the engineer
                          who will need to consider whether the employer would agree to his employee’s
                          request, and whether it is within the engineer’s power to instruct the contractor
                          to make such addition. Obviously in matters of choice or no great cost the resi-
                          dent engineer will assent to reasonable requests, such as colour schemes for fin-
                          ishes. But sometimes during the finishing stages of a construction, the request
                          may be for something expensive or which could delay completion, and it is then
                          necessary to be sure the employer agrees with the request of his employee.
                            When ordering variations the ICE conditions set out the procedure to be
                          followed. All such variations have to be ordered in writing, or if given orally,
                          must be confirmed in writing. The ICE conditions require the contractor to under-
                          take such ordered variations and, in general, they are to be paid for at bill rates
                          or rates based on them. In some instances this may seem harsh on the contractor,
                          since he may be doing work somewhat different from what he expected, and
                          the rates so applied may seem to him too low. But the reverse can also happen,
                          and some of the varied work may leave the contractor with a welcome extra
                          profit, if the relevant rates happen to be set high at tender.
   223   224   225   226   227   228   229   230   231   232   233