Page 229 - Civil Engineering Project Management, Fourth Edition
P. 229

209
                                                                       Variations and claims
                            Extensive variations can make the contractor’s task of constructing the works
                          to his original programme impossible and can seriously affect his costs. They
                          should be avoided if at all possible, but if they occur, the added costs can be
                          taken into account by allowing for them in the rates set under the variation order.
                          But ordered variations must not be so large as to alter the nature of a contract.
                          This problem more usually arises when the employer decides to delete some
                          substantial part of the contract works, such as a complete structure or a length
                          of pipeline. A large deletion may so change the content of the contract that
                          it may have to be re-negotiated, or maybe some agreement has to be reached to
                          reimburse the contractor part or all of his intended profit on the deleted work.
                          Clearly this is a matter for agreement between the employer and the contractor,
                          and could not be ordered as a variation.
                            Under the  ECC conditions (see Section 4.2(f)) the project manager may
                          instruct a change to the works information and this has the same effect as
                          a variation. The effect of such an instruction in the terms of ECC is to create
                          a compensation event; one of the many such events listed in core Clause 60.1.
                          On giving the instruction, the project manager asks for a quotation from
                          the contractor, which is to include both proposed changes to the price and the
                          time for completion. If the project manager does not accept the quotation
                          he may ask for it to be revised or can make his own assessment of the
                          effect of the instruction. The means of assessment depend on which of the
                          options for payment has been selected but can include use of items in any
                          bill of quantities.
                            Under  lump sum contracts the ability to order variations may be much
                          restricted, and may sometimes only be possible by pre-agreement. Normally
                          there will be some contingency money in the contract, which the engineer is
                          authorized to expend on necessary variations. Since there are seldom any unit
                          rates in a lump sum contract, the engineer may have to request a quotation from
                          the contractor for a proposed extra before he orders it. It depends on the con-
                          tract provisions how he deals with a quotation which he thinks is too high.
                          Sometimes he will have no power other than to negotiate a lower price from the
                          contractor. If that fails he either orders the extra at the contractor’s price or does
                          not order it. If it is a matter of some importance he may decide to consult the
                          employer on the matter. On lump sum or turnkey projects, care has to be taken
                          to ensure that any extra required is a true addition, not included in or implied
                          by the overall requirements of the contract. As may be imagined this is a fruit-
                          ful cause of dispute.
                            On some lump sum contracts, while all above-ground work is paid for by
                          means of lump sums, a small bill of quantities may be included for below-
                          ground, that is foundation work, so that it can be paid for according to the
                          prices entered by the contractor and the measure of below-ground work
                          required. This covers the case where the extent of the foundation work may
                          not be exactly foreseeable. Other lump sum contracts may include a schedule of
                          rates to be used for pricing ordered variations, typically adopted in the case of
                          electrical or plumbing contracts where additions of a standard nature are often
                          found necessary.
   224   225   226   227   228   229   230   231   232   233   234