Page 233 - Civil Engineering Project Management, Fourth Edition
P. 233

213
                                                                       Variations and claims
                          that the blinding concrete looks too thin in places and must, as specified, be
                          a minimum of 100mm thick, and within an hour or so the resident engineer
                          receives a signed CVI stating ‘We are to thicken up blinding concrete at so-
                          and-so’. At the bottom of the CVI form is printed ‘and any extra work arising
                          from the above instruction will be charged’. This sort of spurious claim has,
                          of course, to be rejected immediately in writing by the resident engineer.
                          Otherwise, if not contradicted and left on file, it may later be re-submitted by the
                          contractor as a justifiable ‘claim’ long after the nature of the incident has been
                          forgotten. If the resident engineer has, however, given a verbal instruction that
                          justifies a claim for extra payment, he should confirm it in writing with precise
                          details, and require the contractor to submit a detailed account of his costs
                          promptly. He should also keep his own records of the work done by the con-
                          tractor in response to the instruction.

                          17.7 Sheets submitted ‘for record purposes only’


                          When a contractor considers some work entitles him to extra payment but the
                          engineer does not immediately agree, the contractor may suggest that he should
                          submit daywork sheets for it ‘for record purposes only’ (FRPO sheets), so that
                          the quantity of alleged extra work can be agreed. This suggestion may seem
                          reasonable, but it can result in the contractor’s submitting scores (or hundreds)
                          of FRPO sheets for everything, which he thinks he could claim as an extra. He
                          can work on the basis that the more sheets he puts in, the greater is his chance
                          of getting some extra payment, and so he is not over-concerned as to their
                          accuracy or validity. The resident engineer, however, may not have the staff to
                          check so many sheets and may consider it a waste of time to check them if many
                          appear obviously invalid claims.
                            Therefore, on the first occasion when the contractor suggests submitting
                          FRPO sheets, the resident engineer should refer the proposal to the engineer
                          since, once the principle is accepted for one matter, it may be difficult to prevent
                          submission of FRPO sheets for other matters. Under Clause 53 of the ICE
                          conditions the contractor is required to give notice of a claim, and after that is
                          required to submit full details of it. FRPO sheets are not recognized under ICE
                          conditions, nor does the engineer have to evaluate a claim (if payable at all)
                          on a dayworks basis if that is what is suggested (see Section 13.8). Hence the
                          engineer may decide not to agree to submission of FRPO sheets and, if the
                          contractor persists in sending them, he may advise the resident engineer not
                          to reply to them, only to file them, putting notes thereon concerning their accur-
                          acy in case they later form the basis of a properly submitted claim. This avoids
                          time-consuming correspondence and dispute on the sheets, which might
                          inadvertently give the impression the contractor has a claim, which is valid
                          in principle. If, however, dayworks sheets (whether labelled ‘FRPO’ or not) are
                          submitted in support of some properly notified claim regarding extra work, the
                          resident engineer must reply if he considers the sheets are invalid or incorrect,
   228   229   230   231   232   233   234   235   236   237   238