Page 235 - Civil Engineering Project Management, Fourth Edition
P. 235

215
                                                                       Variations and claims
                          costs. The problem is that borings often reveal a range of ground conditions, but
                          unless numerous borings are taken, they seldom disclose the degree of per-
                          sistence and exact location of one particularly difficult condition. In fact, if an
                          experienced resident engineer and the experienced engineer find themselves
                          surprised by the ‘unforeseen event’ it is difficult to maintain that the contractor
                          should have foreseen it. The problem has to be solved on the basis of reason-
                          ableness. A contractor could not reasonably be expected to foresee ground as
                          uniformly bad when trial borings only show it to be of variable quality, good
                          and bad.
                            The advantage of Clause 12 is that it permits many unforeseen conditions
                          to be dealt with efficiently by a contractor with no dispute or problems of
                          payment arising. It offers fair payment to a contractor so he will co-operate
                          with the engineer in dealing with the conditions as effectively and economically
                          as possible. Thus the employer pays only that which is necessary for dealing
                          with the unexpected problem. Quite often the employer has to pay no more than
                          he would have done had the condition been known beforehand and written
                          into the contract. Thus both employer and contractor are fairly dealt with if
                          Clause 12 is properly interpreted.
                            The ECC conditions, (see Section 4.2(f)) include for unforeseen physical
                          conditions on a similar basis, classifying it as ‘a compensation event’ (Clause
                          60.1(12)). The test is worded, however, slightly differently from the ICE con-
                          ditions, being conditions:

                            which an experienced contractor would have judged at the Contract Date to have
                            such a small chance of occurring that it would have been unreasonable for him to have
                            allowed for them.

                            The effect may be much the same as for the ICE wording but has not yet been
                          tested to the same extent by the courts. The outcome for an employer may,
                          however, differ as the boundary between what is covered by the contractor’s
                          prices and what is not, may have altered by the difference in definitions.



                          17.9 Payment for unforeseen conditions


                          A problem arising with Clause 12 claims is assessing the cost of overcoming the
                          unforeseen conditions. When the contractor has notified a claim under Clause
                          12(2) he has to give details ‘as soon as practicable’ of how he is overcoming or
                          intends to overcome the unforeseen conditions, with an estimate of the cost
                          and delay they will involve (12(3)). The engineer can step in and instruct the
                          contractor what to do (12(4)). Since the contractor has notified he is making
                          a claim, the provisions of Clause 53 also apply, which require the contractor to
                          keep records of his work in connection with his claim, and send ‘a first interim
                          account’ giving particulars of the amount claimed to date, followed by further
                          accounts at intervals required by the engineer. The contractor is entitled to
   230   231   232   233   234   235   236   237   238   239   240