Page 227 - Civil Engineering Project Management, Fourth Edition
P. 227

Variations and claims
                                                                                              207
                          reaching a decision on a claim. But irrespective of whether such requirements
                          exist, the engineer should always report major claims to the employer and allow
                          both parties to put their views to him.
                            On very large projects where an ordered variation may incur heavy extra
                          expenditure, it is advisable that the employer is involved in the issue of any
                          order which incurs significant extra cost and many contracts stipulate this. On
                          many such projects, including the Mangla project mentioned in Section 5.6,
                          the engineer will report any proposed major variation to the employer for his
                          agreement, with a technical report in justification. Variation orders can then be
                          issued in two parts: Part I to issue the necessary instructions to the contractor;
                          Part II to set out the terms of payment once discussed with the contractor. Thus
                          urgent variations can be sanctioned by the employer and work can proceed.
                          The employer needs a sufficiently large technical staff available to appraise the
                          technical issues involved without delay. The advantage to the engineer is that
                          the technical issues are thoroughly examined and solutions accepted before
                          commitment to the very large sums which sometimes have to be sanctioned,
                          and the advantage to the employer is that he is fully aware of the changes needed
                          and their effect on the final cost.
                            While variations are normally decided and instructed by the engineer it is
                          not uncommon for contractors to put forward ideas either to save cost or time.
                          Indeed this is encouraged by value engineering procedures and can be a useful
                          way of controlling or reducing the final price. The ICE conditions recognize
                          the potential of such proposals and allow for sharing of any changes in value
                          or time between both parties. Any proposals accepted must be instructed by the
                          engineer before coming into effect.
                            Although the rest of this chapter mostly refers to the powers of the engineer
                          under the contract, this must be taken as implying that the resident engineer
                          must act similarly.



                          17.2 Payment for increased quantities


                          Re-measurement types of contract, such as those covered by the ICE 7th edition
                          (Measurement Version), are let on the basis that the actual amount of work done
                          is not expected to be exactly the same as that estimated from the contract draw-
                          ings. The intention of the contract is that where a change of quantity requires no
                          different method of working by the contractor and does not delay or disrupt his
                          work then the billed rates still apply. However, Clause 56(2) of the ICE condi-
                          tions recognizes that, if there is a considerable difference between the measured
                          and billed quantity, the contract allows a review of the rate to ensure that a
                          proper price is paid. If the engineer is of the opinion that a quantity has changed
                          so much that ‘any rates or prices (are) rendered unreasonable or inapplicable
                          in consequence’, then the engineer, after consultation with the contractor, can
                          increase or decrease such rates or prices. The change in quantity has to be sig-
                          nificant to justify an altered rate.
   222   223   224   225   226   227   228   229   230   231   232