Page 58 - Civil Engineering Project Management, Fourth Edition
P. 58

43
                                             Contract conditions used for civil engineering work
                          D&C contracts are often used when the employer’s main interest is to have
                          some works built as soon as possible, and he need not, or does not wish to be
                          concerned with the details of the design (see Section 1.3). The contractor can
                          therefore start construction as soon as he has enough design ready. But where
                          a project offers a wide range of design options, a design and construct contract
                          may not offer an employer the best service because the options chosen by the
                          contractor may tend to be those which suit his plant and workforce best, rather
                          than the interests of the employer. However, if the ‘Employer’s Requirements’
                          are sufficiently extensive and carefully specified, they can go a long way to
                          ensuring coverage of all the employer’s needs. It should be the aim of the par-
                          ties prior to award of contract to arrive at an agreed scheme and specification
                          for the works. Since this form of contract requires extensive input by tenderers
                          their number should be limited to three or four only.

                          (e) ICE: Term Version


                          Term contracts have been in use for many years typically to cover repair and
                          maintenance of facilities such as road surfaces or flood defences. This new
                          form, based on the ICE 7th edition and issued in 2002, sets out a background
                          contract which stays in place for a prescribed term of years and under which
                          the Engineer can instruct packages of works to be undertaken as necessary.
                          Works are ordered through a Works Order which defines what is required and
                          supplies any drawings or specifications not already in the contract. Payment
                          is made by measurement from a schedule of rates in the contract or  other
                          agreed means.
                            The administration and supervision requirements usually follow those of
                          the Measurement Version and will thus be familiar to most engineers. This
                          form can provide a welcome flexibility for employers in procuring irregular
                          items of work or carrying out services which can be called up as and when
                          needed and at short notice. The form may be suitable for some types of
                          framework arrangement (see Section 1.12).


                          (f) ICE Engineering and Construction Contract


                          This contract was developed from ‘the New Engineering Contract’ (NEC)
                          which was introduced in 1991 and substantially revised in 1993. The NEC is
                          ‘a family of contracts’ comprising versions for construction, sub-contracted
                          works, provision of professional services, and appointment of an adjudicator.
                          The main construction contract was developed and renamed the Engineering
                          and Construction Contract (ECC) which went into a second edition in 1995.
                            The ECC is formed from ‘core clauses’ which set out the general terms of the
                          contract, ‘main option clauses’ which define valuation and payment methods
                          (one of which must be chosen), and ‘secondary options clauses’ for such as
   53   54   55   56   57   58   59   60   61   62   63