Page 61 - Civil Engineering Project Management, Fourth Edition
P. 61

Civil Engineering Project Management
                          46
                          takes over full responsibility for design and construction including any
                          requirements of the employer, and undertakes to produce works which
                          achieve the desired result. There is no independent engineer but an employer’s
                          representative who carries out various administrative and payment functions
                          on behalf of the employer with disputes again referred to a DAB.
                            FIDIC have also produced a short form of contract for short-term projects
                          of a fairly simple nature handled directly by the employer’s staff.
                          4.4 Other conditions for civil engineering
                               or building work


                          GC/Works/1 – General Conditions of Government Contracts for
                          Building and Civil Engineering Works, Edition 3 (1991)


                          This edition is used mainly by UK government departments. They are, in con-
                          sequence, widely used and are available in a number of different forms, for
                          example, for payment by priced bills of quantities, lump sum, schedule of rates,
                          or for design and construct, or supply only contracts. The contract is adminis-
                          tered by a project manager or supervising officer who may be given powers
                          similar to those of the engineer under the ICE conditions, but this depends on the
                          policy of the government department concerned and type of work undertaken.
                            The employer (i.e. government department) takes on some powers exercised
                          by the engineer under ICE conditions, including granting extension of time and
                          deciding some payments to the contractor. Different departments may adopt
                          different approaches in using the conditions, and new methods of contract
                          administration have been tried out from time to time. Earlier editions of these
                          conditions were felt to leave too much of the risk of construction with the con-
                          tractor; for example by allowing neither extra time nor money in the event of
                          bad weather. The 3rd edition of GC/Works/1 published in 1998 shows a more
                          balanced approach but still does not require the project manager to act fairly.


                          Joint Contracts Tribunal Conditions


                          These conditions are not intended or used for civil engineering work but are
                          the most widely used conditions adopted in the building industry; they are
                          described here to show the building industry’s different approach. Buildings
                          will, of course, include many significant elements of civil construction, such as
                          deep foundations or reinforced concrete structures such as a multi-storey car
                          park. The ‘Joint Contracts Tribunal (JCT)’ which produces these conditions com-
                          prises representatives of the RIBA, RICS, ACE, various employers and building
                          contractors and specialist contractors’ organizations and representatives of local
   56   57   58   59   60   61   62   63   64   65   66