Page 60 - Civil Engineering Project Management, Fourth Edition
P. 60

Contract conditions used for civil engineering work
                          4.3 Conditions published by the International
                               Federation of Consulting Engineers (FIDIC)
                          FIDIC ‘Red Book’ Conditions, 4th Edition                             45
                          The FIDIC ‘Red Book’ Conditions, 4th Edition are intended to apply to civil
                          engineering work worldwide. They take the same form as the ICE conditions,
                          but with some variations and simplifications to allow for work outside the
                          UK. Additions can be made to cover local needs and different procedures for
                          payment including payment in different currencies. The 4th edition – sub-
                          stantially revising the 3rd – incorporated changes resulting from consult-
                          ations within the international construction industry and with major
                          international lending agencies. These conditions were accepted by the major
                          lending agencies who recommend or require their use together with addi-
                          tional clauses and amendments proposed by the agencies.
                            An important requirement in FIDIC4 is that the engineer is specifically
                          required to consult with both the employer and the contractor before making
                          a decision on a contractor’s claim for additional payment or extension of the
                          contract period. Another provision of importance is contained in Clause 52(3)
                          which allows for adjustments to payment with respect to the contractor’s
                          overheads if the value of extra works ordered exceeds 15 per cent of the ten-
                          dered sum excluding dayworks and provisional items.


                          1999 New forms


                          In 1999 FIDIC published four new forms. The first is a Contract for Construc-
                          tion to replace the Red Book. Much of the text and the concepts have remained
                          but the whole is re-organized into what was considered a more logical
                          sequence of clauses. The role of the independent engineer is retained who again
                          has to consult with both parties to try to reach agreement on claims and the
                          like, but if this is not possible, to ‘make a fair determination in accordance
                          with the Contract, taking due regard of all relevant circumstances’. The engin-
                          eer’s duty to make final decisions on disputed matters is replaced, however,
                          by use of a Dispute Adjudication Board (DAB) selected by the parties.
                            A second form is for Plant and Design-Build which allows for the contractor
                          to undertake design in accordance with the Employer’s requirements set out
                          in the contract. As the title suggests this is intended both for plant supply
                          and installation and for use where much of the civil works may also be
                          designed by the contractor. This contract again uses an independent engineer
                          to monitor design and construction against the requirements and has the DAB
                          to decide disputes.
                            Additionally FIDIC produced in 1999 a radically different form for engineer,
                          procure and construct (EPC)/Turnkey Projects. Under this form the contractor
   55   56   57   58   59   60   61   62   63   64   65