Page 59 - Civil Engineering Project Management, Fourth Edition
P. 59

Civil Engineering Project Management
                          44
                          bonus, delay damages, and price adjustment. A short form for minor works
                          and a short sub-contract form are also available.
                            The contract requirements are defined in separate sets of data – Works
                          Information and Site Information supplied by the Employer, and Contract
                          Data which set out various pieces of information depending on which options
                          have been chosen.
                            A project manager appointed by the  employer administers the contract on
                          behalf of the employer, assisted by a supervisor on site. A separate adjudicator is
                          appointed to whom the contractor (but not the employer) can take disputes
                          with the project manager or the supervisor for adjudication. But if the employer
                          or the contractor disagrees with the adjudicator’s decision either can have the
                          dispute referred to any final tribunal set out in the contract.
                            The contract attempts to overcome some old problems by several new
                          approaches, but the latter may present some new difficulties. A list of eighteen
                          Compensation Events is prescribed, each of which entitles the contractor to claim
                          extra payment and delay. They include the usual matters of claim such as vari-
                          ation of work, unforeseen conditions, etc. but add unusual weather. The latter
                          is defined as – Weather recorded ‘within a calendar month…at the place
                          stated in the Contract Data…which by comparison with the weather data, is
                          shown to occur on average less frequently than once in ten years.’ The weather
                          data is that supplied by the employer in the Contract Data, and a ‘weather
                          measurement’, could, for instance be rainfall. This definition could give rise to
                          problems of interpretation and may lead to claims even when the weather
                          causes no delay.
                            Another provision is that the contractor’s claims when he experiences a
                          compensation event take the form of quotations which the project manager can
                          accept, return for revision, or reject by advising he will make his own assess-
                          ment in lieu. The problems with this approach are discussed in Section 17.12
                          below. Strict time limits of 2 weeks apply to stages of action and response
                          by both contractor and project manager in respect of such quotations and
                          other submissions. These times are tight and may cause difficulties; failure
                          of the project manager to reply within a specified time limit being itself a
                          compensation event!
                            The stated intent of the drafters of the ECC contract is to stimulate good
                          management. This seems to be achieved by requirements for meetings in a
                          variety of situations, so as to seek advantageous solutions to potential prob-
                          lems, and the tight timetables for responses between the parties.



                          (g) Partnering Addendum


                          This addendum has been issued by the ICE in 2003 to provide for the partners
                          setting down their objectives and any risk sharing provisions formally. The
                          addendum acts as an addition to individual contracts, which may be of any
                          type, and allows for revision as partners leave or are added to a project.
   54   55   56   57   58   59   60   61   62   63   64