                    1.2.5 Performance


                    1.2.5.1 Within 10 days after the Contract takes effect, Party B shall submit to
                    Party A the unconditional, irrevocable and on-demand bank guarantee and
                    advance payment guarantee in favor of Party A from the insurance company. The
                    amount of advance payment guarantee shall 25% of the contract amount
                    respectively. The guarantee institution  shall assume its guarantee obligations
                    independently and expressly waive Party B's right of defense under the Contract.
                    The letter of guarantee shall be acceptable to Party A both in format and essence.

                    1.2.5.2 The validity of advance  payment bond is January 27, 2020 and
                    performance bond valid within 3 months from the contract signing date (January
                    2020). Upon expiration of the guarantee submitted by Party B, the letter of
                    guarantee shall be returned. According  to the general contract, Party B shall
                    extend the validity period of the performance guarantee as instructed by Party A
                    if the actual delivery date of the last batch of goods is later than the expiry date
                    of such letter of guarantee.

                    1.2.5.3 Party B under the Contract shall be solely responsible for the performance
                    guarantee. In case the Final Acceptance Certificate had been issued,if Party B
                    fails to fulfill any or all of its obligations under the Contract or is in breach of the
                    Contract, Party A may issue a notice of claim or default to request Party B to take
                    remedial measures within 5 days upon receipt of such notice or a longer period
                    of time as agreed by both parties. If Party B fails to take remedial measures within
                    the prescribed time, Party A is entitled to deduct the associated amount from the
                    performance guarantee immediately. If the guarantee amount is insufficient for
                    compensating all direct and indirect losses of Party A, Party A is entitled to

                    recover the deficiency from Party B.

                    1.2.5.4 If Party A deducts certain  amount from the performance guarantee
                    according to the Contract, Party B shall neither delay suspend or terminate the
                    performance of its responsibilities and obligations under the contract nor delay,
                    suspend or terminate the ongoing and upcoming work. In the above situation,
                    Party B shall make compensation to Party A according to the actual loss caused
                    by the delay in the delivery time/construction period of Party A; in addition, Party