1.8.4.7 Packing requirements (Provided by Party A).


                    1.8.4.8 Intermittent production plans to be provided by Party B (Provided by
                    Party B).



                    1.9 Requirements on submission of drawings and related data.
                    1.9.1 Party B shall submit three sets of complete instructions to Party A for the

                    unloading, storage, installation, operation and maintenance of all equipment.

                    1.9.2 Design drawings: submission to the Employer and review process.
                    1.9.2.1 Preliminary submission - one duplicable version and five copies.


                    1.9.2.2 Secondary submission - one duplicable version and five copies.
                    1.9.2.3 Submittals for final distribution (drawings issued by the manufacturer):
                    three copies and three CDs.


                    1.9.2.4 “As-built” drawings issued by the manufacturer: two copies and three
                    CDs.
                    1.9.2.5 “As-built” drawings issued by the manufacturer: two copies and three

                    CDs.

                    Party A: PT. BAGUS KARYA
                    Party B: PT. ENERGI INDONESIA PERSADA



                    Legal representative:                           Legal representative:


                    Mr. HENRY KURLI                                 Mr. SUTOYO
                    or authorized representative:                  or authorized representative:











                    Date of signing:                               Date of signing: