Page 50 - puget sound energy community energy programs
P. 50

Chapter 4


              Trench and          You must provide a 12-inch layer of sand above and a 4-inch layer of sand bedding
              backfill            below the utilities before backfilling (see Figure 22). If native backfill is completely free of
              requirements        foreign objects and rocks in excess of 8 inches in diameter, sand shading over utilities
              for primary         can be reduced to 6 inches after compaction.
              electric line       You are responsible for the following:
              extension
              trenches (with      •   Completing backfill as soon as practical after facilities are placed and inspected.
              PSE gas)            •   Carefully placing backfill to prevent damage or movement of the cables or conduit.
                                  •   Cost of damages to PSE facilities caused by improper backfill or compaction.
                                  •   Relocation costs due to change in grade or alignment.
                                  CAUTION: Do not use a compactor directly over the power conduit(s) until at least
                                  30 inches of backfill is in place so that the compactor will not damage the cables or
                                  conduit. Do not penetrate the soil deeper than 3 inches during compaction with a
                                  backhoe compactor.


              Vaults


                                 PSE is responsible for furnishing and installing all primary vaults and secondary
                                 handholes required for your electric service.

              Vault              1.  Locate the vault according to PSE’s work sketch drawing.
              excavation         2.  Determine a suitable place to put the spoils (at least 2 feet from the edge of the
              procedure             excavation).
                                 3.  Excavate so the vault is in correct alignment with the trench and so that conduits
                                    for primary voltage cables (if required) can be brought straight into the front half of
                                    the vault.
                                 4.  Dig a hole large enough to accommodate the transformer or junction box vault and
                                    allow for easy installation and compaction (see Figures 23 through 26).
                                 5.  Remove debris and level the bottom of the excavation.
                                 6.  Prepare the bottom of the excavation so that the vault will rest on solid undisturbed
                                    earth with a 6-inch base of crushed rock. This prevents vault settling.






























                                                                                                            41
               Electric Service Handbook 2017 — Single-Family Residential Projects                          41
   45   46   47   48   49   50   51   52   53   54   55