Control of Industrial Major Accident Hazards (CIMAH) Report Page 3
Ranhill SAJ Holdings Sdn. Bhd. Revision 01
Summary of Findings Date Aug 2019
SECTION No. ITEM FINDINGS
iv Maximum number KT1
of persons at the Max day population : 17
site Max night population : 3
KT2
Max day population : 10
Max night population : 3
Refer Part B.4.0
v Land use and Surrounded by palm oil and rubber
distribution of the plantation.
population in the
vicinity of the Population in the immediate vicinity are a
industrial activity housing area, small factory and staff
site quarters.
Refer Part B.5.0
vi Emergency The Company maintains the list of
Services emergency contact as in the Emergency
Response Plan.
Refer Part B.6.0
C: Information in i Staffing The Company has established the suitable
relation to the arrangements manning for safe operation of the plant.
safety and
health system Refer Part C.1.0
of management
ii Safe operation The Company has established HSE
management management system, with safe work
practices as to ensure safe operation
including emergency response plan.
Refer Part C.2.0
iii Staff training Personnel who are engaged in the plant
operation are provided with training and
competence requirement.
Refer Part C.3.0