3.2 Cold Room






       The  cold room  will normally be purchased
       directly  by  the  franchisee  for  a  Self-Build  or
       DPUK&I Ltd for a corporate build, and supplied
       and installed by a specialist sub-contractor.

       The Shopfitting Contractor will be required to:
       •  Provide normal attendance to the specialist
          sub-contractor  and  to  coordinate  the
          installation of  the  cold room  into  his works
          programme.
       •  Ensure that the floor is flat and level and that
          the floor finishes are laid under the cold room
          prior to its installation
       •  Provide a suitable ‘washing machine type’
          trapped waste on the nearest suitable drain
          run  for  the  coldroom  condensate.  Where
          this is not possible, a condensate pump will
          be supplied and installed by the cold room
          manufacturer,  but  a  suitable  discharge
          point will still be required.

       The coldroom must incorporate  both an
       emergency  light  and  a  brighter  working  light.
       These will normally be supplied and installed by
       the coldroom supplier.


       Emergency  lighting  to  be  connected  by
       electrician for final test / commissioning.