New Store Opening Workflow

        Project Programme (weeks)                                                           Key Stage

         0     4      8     12     16     20     24     28    32     36     40

                                                                                            NSC Approval



                                                                                         Cost Sheet Approval


                                                                                             Instructions



                                                                                        On Site Briefing Meeting



                                                                                        Prelim Layout Approval


                                                                                           Change of Use
                                                                                         - Planning Application


                                                                                               Legals



                                                                                    Change of Use - Planning Consent


                                                                                          Shop-fit Information



                                                                                        Discharge of Conditions



                                                                                          Statutory Approvals


                                                                                               Legals


                                                                                    Tender / Appointment of Principal
                                                                                             Contractor


                                                                                        Pre-start Anchor Meeting



                                                                                            Mobilisation



                                                                                             Start on Site


                                                                                            Construction



                                                                                        Completion / Handover


                                                                                       Post Completion Inspection