DPG and their  Design Team will  submit drawings to form  a Building Control
              Statutory Approvals     application to BRCS (DPG’s incumbent Building Control  Approved Inspector) for
                                      sites in England and Wales; or  the relevant Local Authority  for  sites in Scotland and
                                      Northern  Ireland.  Applications will be developed to  a ‘plans approved’ stage.

                                      Franchisee  will be responsible (either  directly or  via the  appointed Principal Contractor)
                                      for  notifying Building Control  of the  proposed start on  site date, organising  and
                                      managing  all  Building  Control  site  inspections  and  site  certification  documentation.
                                      Copies  of  all  documentation  to  be  forwarded  to  the  DPG  Project  Manager.

                   Legals             Where applicable, DPG Project Manager to attend site and sign off any Landlord’s / developer’s
                                      shell works prior to lease completion.
                                      DPG  Site  Acquisitions  Surveyors  /  Solicitors  to  provide  confirmation  of  lease  completion  to
                                      franchisee.
            Tender / Appointment of   Franchisee to obtain quotations from approved contractors and suppliers, and appoint a
             Principal Contractor     Principal Contractor

                                      - Shop fitting works
                                      - Standard equipment package
                                      - Computer systems
                                      - Telephone systems
                                      - Utilities & BT
                                      - CCTV
                                      - Security systems
                                      - Fire alarm
                                      - Fire safety equipment
                                      DPG Project Manager to arrange meeting on site at least 2 weeks prior to proposed start on
            Pre-start Anchor Meeting  site date.
                                      Pre-start meeting attendance by franchisee, Domino’s Project Manager, appointed Principal
                                      Contractor, Principal Designer and Architect.
                                      Additional attendance may include the franchisee operations team, Structural Engineer
                                      (where applicable) and M&E specialist sub-contractors as required.

                                      Franchisee to liaise with key suppliers, arrange delivery dates and organise site access.
                Mobilisation
                                      Franchisee to ensure that orders are placed to allow works to start on site in accordance with
                                      the agreed construction programme

                                      Franchisee to check that all insurances are in place
                                      Franchisee to check all drawings and construction information prior to orders being placed.
                                      (DPG will not accept responsibility for any errors made)


                 Start on Site        Franchisee to ensure that relevant Building Control body have been notified of confirmed start
                                      on site date.
                                      Principal Contractor begins work. Site to be secured and set up as an appropriate work place,
                                      including provision of welfare facilities.
                                      Principal Contractor to progress the works diligently and in complete accordance with all Health
                Construction          &  Safety  legislation,  statutory  approvals,  construction  information  and  Domino’s  shop  fitting
                                      specification / brand guidance.

                                      Franchisee to agree time and date of store opening with Principal Contractor.
            Completion / Handover
                                      Principal Contractor to handover completed project to franchisee in accordance with agreed
                                      protocol, including final inspection of workmanship and brand standards.

                                      Franchisee to liaise with Principal Contractor, to ensure that all test / commissioning certificates,
                                      as-fitted  information,  statutory  consent  notices,  EPC  report,  Building  Control  final  approval
                                      notices and any other relevant documents are provided in the O&M manual at handover.



                                      DPG Project Manager to carry out final site inspection and review compliance with Domino’s
           Post Completion Inspection  shop fitting specification / brand guidance upon completion of the project.


                                      Administration and development fee for self-build projects is £1,000

                                                                                                                9
   4   5   6   7   8   9   10   11   12   13   14