Page 423 - Installation Training Binder FIT1-3
P. 423
Depending on the size of the containment, some Hawk systems may include
retainer brackets (HWK-HCAL or HWK-HCAS). (If the containment system does
not contain retainer bars, skip to next step.) Slide “H” channel into retainer
bracket as shown in Figure 25. Lay retainer bars as shown in Figure 26.
Figure 25
Retainer bar For
Systems over 96”
Figure 26
When installing multiple cabinets, align barriers the “H” channels as shown in
CAD Diagram. Align “H” channels as close as possible with cabinet joints to
allow access to cabinet door (Figure 27). Barrier sizes and “H” Channel spacing
must be defined and requested at time of ordering.
UPS Battery Battery
Cabinet Cabinet Cabinet
Figure 27
“H” Channels are aligned with cabinet joints to enable
“Hawk” Barriers to be removed to allow cabinet doors to
open, when requested at time of ordering.
EnviroGuard 800-206-9884 Fax 909-624-1772 www.egsintl.com
10/08 rev. A Hawk System Retrofit Installation Setup Instruction - 10 -