Depending on the size of the containment, some Hawk systems may include
                   retainer brackets (HWK-HCAL or HWK-HCAS).  (If the containment system does
                   not contain retainer bars, skip to next step.)  Slide “H” channel into retainer
                   bracket as shown in Figure 25.  Lay retainer bars as shown in Figure 26.














                                                         Figure 25



                  Retainer bar For

                  Systems over 96”







                            Figure 26


                   When installing multiple cabinets, align barriers the “H” channels as shown in
                   CAD Diagram.  Align “H” channels as close as possible with cabinet joints to
                   allow access to cabinet door (Figure 27).  Barrier sizes and “H” Channel spacing
                   must be defined and requested at time of ordering.



                            UPS          Battery        Battery
                           Cabinet       Cabinet       Cabinet







                                                                          Figure 27



                                    “H” Channels are aligned with cabinet joints to enable
                                    “Hawk” Barriers to be removed to allow cabinet doors to
                                    open, when requested at time of ordering.






                   EnviroGuard  800-206-9884     Fax  909-624-1772                     www.egsintl.com

                   10/08 rev. A         Hawk System Retrofit Installation Setup Instruction         - 10 -
   418   419   420   421   422   423   424   425   426   427   428