Page 421 - Installation Training Binder FIT1-3
P. 421
G. Sealing the Liner to the Rack
1. Ensure that the liner is laying flat on the floor all around the rack.
2. Use double sided tape if liner is curled, to secure into position.
3. Clean rack and liner where they meet (use damp cloth).
4. Remove any oil or grease from the rack (use non-volatile cleaner).
5. Apply a bead of sealant around the base of each stanchion to seal the
liner to the rack (Figure 19).
NOTE: Use rubber or latex gloves to protect hands from the sealant.
6. Seal with NP1(UL Approved NP1 Provided by EnviroGuard) (Figure 20).
Bolt holes and Bolt heads
Liner bonds
Open welds on rack
Figure 19 Figure 20
H. Barrier Layout
1. Lay out all “Hawk Barrier Walls” on the floor around the liner according to
the CAD assembly drawing (Figure 21).
Figure 21
EnviroGuard 800-206-9884 Fax 909-624-1772 www.egsintl.com
10/08 rev. A Hawk System Retrofit Installation Setup Instruction - 8 -