Page 45 - manual_V5_11_9_2018_Html5
P. 45

Figure 4-13: Sources and Sinks (Head Dependent) sub-menu (for Zone conceptual features).
               If the time-varying option is selected, LM click on ‘Transient’ button to open the ‘Transient Data for Lake
               Stage’ menu (see Figure 4-14). Indicate the starting data and time with the text boxes next to ‘State Date’
               (year, month, day, hour). Then, provide the following inputs for each timestep: TimeN – or the number of
               days since the starting date and time; and ValueN – the stage value corresponding to TimeN.  The stage
               values may be entered in any units; however, if meters are not used, make sure to enter the appropriate
               multiplier in the text box next to ‘Multiplier to meter:’. For example, to convert from ft. to m, enter 0.3048,
               as 1 ft.=0.3048m. After all desired changes have been made, LM click the ‘OK’ button.  Or click ‘Cancel’
               to discard all changes and close the sub-menu.


































                             Figure 4-14: Sub-menu for editing transient lake (or other source/sink) stage data.