Page 76 - SAPEM-Chapter-10-2nd-edition-2014
P. 76

South African Pavement Engineering Manual
                                              Chapter 10:  Pavement Design

              In  a  jointed  concrete  pavement,  erosion  of  the  supporting  layer  not  only  results  in  pumping,  but  also  causes
              displacement of subbase fines from the slab downstream of the transverse joint towards the upstream side of the
              joint.  Accumulation of fines below the upstream slab causes it to rise, whereas the downstream slab goes down due
              to the void.  This results in a step at the transverse joint, also called faulting.  Usually the void that develops under
              the  downstream  side  of  the  transverse  joint  results  in  transverse  cracking  about  2  metres  away  from  the  joints.
              Faulting affects the riding quality of the road, and is rectified by grouting the voids underneath the slab followed by
              grinding down the step at the joints.

              Structural failures under traffic loading usually occur at, or close to, transverse joints or shrinkage cracks.  This is
              because of a break in the uniformly constructed pavement, a decrease in the ability of the pavement to transfer the
              load across the joint/crack, and, thus an increase in stress in the concrete slab.  The design philosophy therefore is
              to ensure proper load transfer at the joint/crack under moving traffic loading.  This capability to transfer loads across
              the joint/crack is defined in terms of relative vertical movement as the load moves across the joint/crack.  This is
              measured by moving a wheel load across the joint/crack, or by using the FWD.  With the FWD, the difference in
              deflection between the loaded slab and the adjoining slab on the other side of the joint/crack is measured.  The
              calculated  relative  vertical  movement  is  used  in  cncPAVE  as  an  input  into  the  calculation  of  tensile  stress.  The
              measured relative vertical movement on existing pavements can be used to design overlays.  As a guide, the relative
              vertical movement suggests the following rehabilitation options:
              •  Relative vertical movement < 0.09 mm: A combination of asphalt layers with modified binders is successful.
              •  Relative vertical movement > 0.10 mm:  Reinforced concrete pavements with or without steel fibres are
                 recommended to achieve an acceptable life expectancy.
              •  Relative vertical movement > 0.20 mm:  Methods such as crack-and-seat, installing dowel bars, grouting at
                 joints/cracks, or, slab repairs to improve the relative vertical movement, should be considered before overlaying
                 the old concrete slab.

              Punch-outs, i.e., loose blocks about 300 mm x 300 mm in size, are only found in CRCP.  Punch-outs develop where
              transverse  shrinkage  cracks  are  relatively  wide  and  are  closely  spaced  (load  transfer  at  these  cracks  is  limited),
              pumping is occurring and longitudinal cracks occur between these transverse cracks.

              Once cracking of the slab becomes excessive, resulting in loose blocks, punch-outs and a loss in riding quality, it is
              defined as a shattered slab, which then requires a full depth repair or even slab replacements.  Methods for this are
              described in the Concrete Road Construction Manual (C & CI, 2008).

              Overlays  using  asphalt  or  concrete  are  also  considered  as  a  long  term  rehabilitation  option.   To  avoid  reflection
              cracking, the type of asphalt mix must be carefully selected to resist the relative vertical movement at joints and
              cracks.

              Before overlays are placed, and as routine maintenance,  severely cracked or  shattered  slabs should  be replaced,
              cracks should be cleaned out (routed) and resealed with silicone or bitumen rubber.

              5.3.2.3  Appropriate Rehabilitation Options:  Block Pavements
              Block pavements can exhibit deformation as in flexible pavements.  Cracking of the concrete blocks can occur which
              generally indicates a strength problem of the concrete used for the manufacturing of the blocks.  Should the block
              pavement need to be repaired, the blocks can be removed, the support reinstated and then the same blocks relaid,
              provided the blocks are undamaged.

              5.3.2.4  Appropriate Rehabilitation Options:  Composite Pavements
              Composite  pavements  are  pavements  that  are  rehabilitated  by  using  concrete  and  bituminous  materials
              together.   For example, concrete overlays can be constructed on flexible pavements.  This is often referred to as
              white-topping.  A special case is an Ultra-Thin Continuously Reinforced Concrete Pavement (UTCRCP), which is at
              least 50 mm thick and constructed on an existing flexible pavement (see Chapter 9: 12.2.2).  Full or partial depth
              concrete inlays are constructed in the slow lanes of flexible pavements, where the heavy traffic has increased to such
              an extent that flexible pavements are no longer cost effective.   The fast lanes of heavily trafficked roads can be
              constructed as a flexible pavement and the middle and slow lanes, or only the slow lane, in concrete, to cater for the
              heavier loads.

              Concrete  roads  with  insufficient  texture  depth,  or  where  the  riding  quality  is  unacceptably  low,  are  repaired  by
              regrinding  to  restore  the  skid  resistance  and  riding  quality.   However,  this  type  of  restoration  requires  expensive
              specialised equipment and, if it is not required on large scale, is likely to be unfeasible.   Pavements which have been
              heavily repaired, or  show severe faulting of joints and cracks, are overlaid with  asphalt or concrete.  Where new


                                       Section 5:  Pavement Investigation and Design Process
                                                         Page 65
   71   72   73   74   75   76   77   78   79   80   81