Page 123 - JBAS Realty-Bernardon Proposal for Design Services (revised)
P. 123

The New Project's Name
                                                                                                        5/19/2022
                                                                                              revised July 8, 2022





          WORK PLAN



          The project phases we have planned in our work activities include:



                    TASK          SCHEMATIC PHASE

                       01             •   Project kick-off meeting.
                                      •   Code research.
                                      •   Calculations.
                                      •   Investigation of mechanical, electrical, plumbing systems to accomplish the
                                          desired result for the project.
                                      •   Preliminary document defining the VRF system and up to two (2) MEP/FP
                                          system alternatives for Owner/Architect review and budgeting.
                                      •   Review of any special needs and identifying the most appropriate means of
                                          achieving operational requirements.
                                      •   Prepare and submit S&M applications with that appropriate utility companies
                                      •   Preliminary coordination of utilities with Civil.
                                      •   Attendance at the allocated project/design meetings during this phase.
                                      •   Preparation of a narrative based schematic submission for owner review and
                                          budgeting.




                    TASK          DESIGN DEVELOPMENT

                       02             •   Incorporate client, construction manager, and design assist team input from
                                          schematic including MEP/FP system selections.
                                      •   Perform preliminary equipment selections and mechanical and electrical
                                          space requirements based on budgetary input.
                                      •   Provide proposed domestic water room/fire pump room layouts, plumbing
                                          riser locations, proposed utility connection locations.
                                      •   Provide proposed main electrical room layouts, corridor lighting and power
                                          layouts, electrical distribution closet layouts.
                                      •   Provide proposed common area mechanical shaft locations, corridor
                                          ductwork distribution, and rooftop mechanical equipment layout.
                                      •   Provide criteria for retail space MEP/FP systems.
                                      •   Provide preliminary parking garage lighting, power, ventilation, and drainage
                                          design.
                                      •   Preparation of six (6) typical enlarged unit mechanical, electrical, and
                                          plumbing plans for each the hotel and apartment/condo building
                                          owner/architectural review.


          Advanced Engineering Inc. | 5561 Pennell Road, Media PA 19063 | 610-361-0700                     9/21
   118   119   120   121   122   123   124   125   126   127   128