Page 472 - Bahrain Gov Annual Reports (III)_Neat
P. 472
66
Building Extensions.—Work completed for the Department by private contractors and
the P.W.D. consists of the raising ol the Power House Switchboard roof to give better ventilation.
The building of Main Offices and Power House annexe for new Generating Plant and its equipment.
The recovery of a plot of land East of the Power House and the building of the foundations for the
new Water Distillation Plant. Also two sub-stations for the electricity distribution system. A
further sub-station was built for the Department by the Muharraq Municipality. These new sub
stations have replaced the metal Kiosk type which were not large enough to house the larger trans
formers required for increased power distribution.
FUTURE PROSPECTS
(a) Additional Generating Plant.—Enquiries have been made for the supply of additional
generating plant either in one single unit or two separate units of capacities between 600 kW and
750 kW. This new plant is required to provide additional power and lighting demands and also
reserve capacity to enable regular maintenance and repairs to be carried out without curtailment of
supply.
It is planned to provide not less than 1,400 kW within the next two years as follows:
Now available (sets 4 and 5) .. 506 kW.
Due to arrive—March 1948 .. .. 300 kW.
To be ordered upon receipt of ■■ ■■ i 600 kW.
quotations (alternatively) 1 750 kW.
(b) Building Extensions.—
(1) An annexe to the Blacksmith Shop will be provided to house a steel hardening muffle.
This plant is urgently required to facilitate repairs and manufacture of tools and
generating plant spare parts. It is also intended to move the electric welding plant
from the Blacksmith shop to this new shop owing to congestion in the former.
(2)
A prc-fabricated steel frame building will be erected on a prepared site to house the
water distillation plant of 10 Ton/24 hours capacity.
(3) When the requisite land has been purchased from a private owner, the building of a
compound with servicing shed and ramps for heavy and medium M.T. vehicles
will be commenced. This is a most urgent requirement as the present facilities
are inadequate for the efficient repair and servicing of Government vehicles.
(4) reaui^01^ SU^*station building to contain an increased capacity transformer is
scheme ° COm^c*e ^le rearrangements of the Manama electricity distribution
The requisite plot of land has been acquired for this purpose.
(c) General.—
(1) To provide economy in the use of artesian well water required for the generating plant
cooling systems, it has become necessary to place an order for the supply of a water
cooling tower. The estimate consumption of artesian well water during the next
year will approximate 2,88,000 gallons per day and in the following year it will further
increase after the installation of additional generating plant. The provision of a
water tower and surface tank will enable the discharge water from the circulating
pumps to be retained in constant circulation as opposed to being lost by discharge
into the sea.
(*> The existing artesian well which supplies the water for the engine cooling systems
requires the draw off capacity to be increased. The present pipe line of 3' dm*
will be increased to 6'.
When the Government water scheme is functioning the use of this well will be dis
continued but the necessity for the cooling tower will still exist.
I